Institutional Building Cost Estimator (Hospital, School, College)
Enter beds, classrooms or students and your local rates to get floor area, cost by element, specialised services, equipment and a phased cash flow.
S'executa al teu navegador. Els fitxers mai no surten del dispositiu. Mira com comprovar-ho
…
Com es fa
- 1Choose the type
On Inputs, pick hospital, school or college; the element mix and equipment row are set for that type.
- 2Size the brief
Enter the number of beds, classrooms or students and the floor area per unit, or a total area.
- 3Enter rates
Type your local all-in rate per unit of area, the quality level and the allowances.
- 4Review elements
On Elements and Breakdown, check the specialised services and equipment allowance.
- 5Phase the work
On Phasing, enter phases with share, start month and duration and read the quarterly spend.
- 6Print and compare
Print the estimate, export CSV or save scenarios for different sizes.
Sobre aquesta eina
Public bodies, trusts, charities and private operators planning a hospital, school or college usually start from the service they want to provide, such as 120 beds or 30 classrooms, rather than from a floor area. This estimator turns that brief into an order-of-cost estimate. Choose the building type and enter the number of beds, classrooms or students and the gross floor area per unit, which includes wards or teaching rooms plus circulation, plant, support and administration space. The default areas are planning assumptions you should check against the space standards that apply to you; you can also type a total floor area directly. The cost is split into substructure, frame and roof, envelope, mechanical and plumbing, electrical, internal finishes and external works, plus specialised services that set these buildings apart: medical gases, clean rooms and theatre ventilation and nurse call for hospitals, laboratories and workshops for schools, and laboratory services and fume extraction for colleges. An equipment allowance per bed, classroom or student covers loose equipment and furniture that are not part of the building.
Cost per bed, classroom or student
Next to the cost per square metre and per square foot, the tool shows the cost per unit of service, which is how many funding bodies compare projects. Change the area per unit to see how a more generous or tighter design moves the total.
Phasing
Large institutional projects are often built in phases so services keep running. The phasing tab lists each phase with its share of the total cost, a start month and a duration, and spreads the spend into quarters with a stacked chart and table. A warning appears if the shares do not add up to 100 percent.
Allowances, plan and files
Contingency, design fees, escalation and tax are added to the construction cost, and the payment plan gives stage amounts and dates with a monthly cash flow. Save scenarios, print the estimate, export CSV, save JSON and undo changes.
Limits
Areas per unit, specialised service shares and equipment allowances are editable planning assumptions, not standards, and all rates are yours. Land, enabling works off site, financing, operating costs and major medical equipment beyond the allowance are not included. This is an order-of-cost estimate, not a quotation or professional advice.
Exemple resolt
A 120-bed district hospital is planned at 110 square metres of gross floor area per bed, 13,200 square metres. With a local all-in rate of 2,100 per square metre the building costs 27,720,000, of which specialised services (medical gases, theatre and isolation ventilation, nurse call and IT) are 6,098,400. A medical equipment allowance of 18,000 per bed adds 2,160,000. With 10 percent contingency, 9 percent fees and a year of 4 percent escalation, the total is about 37,259,000, about 2,823 per square metre or 310,500 per bed. Built in two phases, 60 percent over months 0 to 24 and 40 percent over months 12 to 30, the spend peaks in the middle quarters.
En resum
- Categoria: Negocis i feina
- S'executa al navegador, sense registre, sense pujar res.
- La informació que introdueixes es queda al dispositiu.
- Disponible en anglès.
- Contingut revisat per última vegada:
- Font oficial: RICS New Rules of Measurement NRM 1 (order of cost estimating and elemental cost planning); International Construction Measurement Standards (ICMS)
Preguntes freqüents
How much floor area does a hospital bed need?
It varies widely with the services offered. A small general hospital may need 80 to 120 square metres of total floor area per bed once wards, theatres, imaging, outpatients and support are included, and specialist hospitals more. Check your national health building guidance.
How big is a classroom?
Many standards set 50 to 70 square metres for a general classroom. The default 105 square metres per classroom includes corridors, toilets, staff rooms, halls and plant; change it to match your brief.
What are specialised services?
Systems these buildings need beyond a normal office: medical gases, clean air for operating theatres and isolation rooms, nurse call and pneumatic tubes in hospitals, and laboratory gas, water and fume extraction in schools and colleges.
Is medical equipment included?
Only through the equipment allowance per unit. Major imaging equipment such as MRI or CT scanners is usually budgeted separately with supplier quotes.
Can I enter the floor area directly?
Yes. Type a total floor area and it overrides the area per unit. The cost per unit still uses the number of beds, classrooms or students.
How do I model a phased project?
On Phasing, add each phase with its share of the cost, start month and duration. The quarterly table and chart show how much is spent when.