Calculadora de marge del constructor i variació de preus

Enumereu cada variació amb el seu cost i estat d'aprovació, estableix el vostre marge, i veure els preus de la variació, GST i el nou total del contracte.

S'executa al teu navegador. Els fitxers mai no surten del dispositiu. Mira com comprovar-ho

…

Com es fa

  1. 1
    Introduir el contracte

    Escriu la suma original del contracte.

  2. 2
    Marge

    Escriu el marge per a les variacions.

  3. 3
    Variations de la llista

    Escriu cada un com a número, descripció, cost i aprovats sí o no.

  4. 4
    Llegeix el registre

    Veure preus, GST, estat i la nova suma del contracte.

  5. 5
    Obtenir la signatura off

    Enviar les variacions pendents al propietari per a la seva aprovació escrita.

Sobre aquesta eina

Variations are changes to the work in a building contract: an upgraded benchtop, extra power points, rock found during excavation, or an item the owner deletes. They are one of the main causes of disputes between builders and owners. Home building laws in every state require variations to be in writing, with a description and price, and agreed by the owner before the work is done, with limited exceptions. Builders usually add a margin to the cost of a variation to cover overheads and profit, often 15 to 25%, and then GST at 10%. This calculator prices each variation with your margin and GST, keeps a register showing which are approved and which are still pending, works out the adjusted contract sum, and shows how much the variations have changed the original price.

Who this is for

Builders, renovators and trade contractors who price variations, and home owners who want to check variation claims.

How a variation is priced

Variation price = cost of labour and materials × (1 + margin) + GST at 10%. For a credit, such as a deleted item, the cost is entered as a negative number and no margin is added, though contracts can say otherwise. Your contract may set the margin for variations; use that figure.

Entering variations

Write one variation per line: number, description, cost excluding GST and margin, and whether the owner has approved it (yes or no). For example, `V1, Upgrade benchtop to stone, 4200, yes`.

The register

The table shows each variation's cost, the price after margin, the GST and the total, with its status. The summary gives: - the original contract sum including GST, - approved variations, - the new contract sum, - pending variations still to be agreed, - the percentage change from the original price, - the margin earned on approved variations.

Getting variations right

- Put every variation in writing before the work, with a description, price and any change to the completion date. - Get the owner's signature or written approval. - Number variations and keep a running register. - Include variations in progress claims only once approved. Some states set rules for variations required by an authority or emergency, and some limit when a builder can claim for work done without a signed variation.

For owners

Ask for the cost breakdown and the margin used. Compare the price with what you would pay for the item separately. Check whether a variation also extends the completion date.

Worked example

On a A$385,000 contract including GST, with a 20% margin: an upgraded stone benchtop at A$4,200 cost, six extra power points at A$780 and a garden shed deleted for a A$2,400 credit add A$3,934 to the contract, a 1.0% increase. Rock excavation at A$6,500 cost (A$8,580 with margin and GST) is pending.

Limits

An estimate, not legal advice. Your contract terms and your state's home building laws decide how variations must be made and paid.

Exemple resolt

Tres variacions aprovades afegeixen 3.934 dòlars australians a un contracte de 385.000; una per valor de 8.580 està pendent.

En resum

Preguntes freqüents

Com fan els constructors les variacions de preus?

Cost més un marge, sovint del 15 al 25%, més GST.

Les variacions han de ser per escrit?

Sí, les lleis de construcció d'habitatges en cada estat requereixen variacions escrites en la majoria dels casos.

Es suma el GST a les variacions?

Sí, al 10% per a un constructor registrat.

Com es maneixen els elements eliminats?

Com a crèdit, introduir un cost negatiu.

Pot un constructor cobrar per variacions no signades?

Sovint no, o només en casos limitats; comproveu la llei del vostre estat.

S'emmagatzemen les meves dades?

Només en el teu navegador.

Totalment gratisSense cost, sense registre
Els fitxers es mantenen privatsTot funciona al teu navegador
Fàcil en el teu idiomaDisponible en molts idiomes