Formwork and Shuttering Area and Cost Calculator

List concrete members with their sizes and counts, set sheet size, reuse and prop spacing, and get shuttering area, sheets, prop hire and labour.

Roda no seu navegador. Seus arquivos nunca saem do seu dispositivo. Veja como conferir

…

Como fazer

  1. 1
    List the members

    Add a row for each group of identical members with type, sizes a, b and c and the count.

  2. 2
    Check the meaning of a, b, c

    Each type in the drop-down tells you which dimension goes where.

  3. 3
    Set sheets and props

    Open Sheets, props and factors to set sheet size, reuse, prop spacing and hire days.

  4. 4
    Enter rates

    Type plywood, batten, prop hire, release agent, nails and labour rates on Prices.

  5. 5
    Review the areas

    Use the Drawing and Members tabs to see where the contact area comes from.

  6. 6
    Print or export

    Print the materials list or download the CSV for your site engineer.

Sobre esta ferramenta

Formwork, called shuttering in South Asia, often costs as much as the concrete it holds, yet it is the line most home builders guess. Contractors measure and pay it by contact area: the surface of the form that actually touches wet concrete. That area depends on the member. A slab is mostly soffit, a column is all sides, a beam is a soffit and two sides below the slab, and a stair flight has a sloping soffit, risers and two stepped sides. This calculator lets you list every concrete member of a floor or a whole frame with its three dimensions and how many there are. It works out the contact area and the soffit area that has to be propped, then turns those into plywood sheets allowing for the number of times each sheet can be reused, adjustable props on a grid you choose, battens or runners, release agent, nails and ties, and fixing and stripping labour per area. The Drawing tab charts contact and soffit area by member, so you can see where the formwork goes, and the Members tab lists every row for checking.

Contact area by member

A slab is its plan area plus the edges. A beam is its length times the width plus twice the depth below the slab, because the slab form covers the top. Rectangular columns, footings and pile caps use their perimeter times the height or depth; round columns use pi times the diameter times the height. A wall has two faces and two ends. A stair flight uses the inclined soffit, the total rise times the width for the risers, and two stepped side shutters.

Reuse and props

Good plywood can be used five to eight times on slabs and beams before the face is too worn, and steel or aluminium systems far more. Sheets are therefore divided by the reuse count you enter. Props are counted on a square grid under every soffit and multiplied by the hire days, which depend on how long the concrete must stay supported.

Limits

This is a quantity and cost estimate, not a formwork design. It does not check prop loads, bracing, form pressure or the stability of falsework, and it does not set striking times. Those come from your structural engineer, the formwork supplier and the concrete code. Steel or system formwork rented by the square metre can be priced by changing the plywood line.

Exemplo prático

One floor of a small framed house: a 12 by 9 metre roof slab 125 mm thick, seven beams 230 by 300 mm below the slab, twelve 230 by 300 mm columns 3 metres high, twelve 1.5 metre square footings 450 mm deep, two stair flights and a small tank wall. The contact area comes to 277 square metres, of which 131 square metres is soffit needing props. With 2.97 square metre sheets used five times and 8 percent waste the job needs 21 plywood sheets, 150 metres of battens, 163 props for 14 days, 14 litres of release agent and 34 kg of nails and ties. At the sample rupee rates the estimate is about 127,500, roughly half of it labour.

Resumo rápido

Perguntas frequentes

What is contact area?

The area of formwork surface that touches the concrete. It is the standard way to measure and pay for formwork because it reflects the material and labour used.

Why do beams use the depth below the slab?

The top of the beam is formed by the slab soffit, which is already counted. Only the beam bottom and the two sides below the slab need extra shuttering.

How many times can shuttering plywood be reused?

Film-faced plywood is often reused five to eight times with care, and plain plywood fewer. Steel and aluminium panels last for dozens of pours. Enter your own figure.

How close should props be?

About 0.9 to 1.2 metres apart each way under typical house slabs, but the spacing depends on slab thickness and the prop system, so follow your engineer or supplier.

Can I estimate rented system formwork?

Yes. Set reuse to 1 and change the plywood line to a hire rate per square metre, or add your own price items for panels and ties.

Is anything sent to a server?

No. The member list, rates and scenarios are processed and stored in your browser only.