Gebouwersmarge en variabele prijzencalculator

Maak een lijst van elke variatie met de kosten en goedkeuring status, stel uw marge in, en zie de variatie prijzen, GST en het nieuwe contract totaal.

Draait in je browser. Je bestanden verlaten je apparaat nooit. Zie hoe je dit controleert

…

Zo doe je het

  1. 1
    Inschrijven van het contract

    Typ het oorspronkelijke contractbedrag.

  2. 2
    Stel de marge in

    Typ de marge voor variaties.

  3. 3
    Veranderingen in de lijst

    Schrijf elk als nummer, beschrijving, kosten en goedgekeurde ja of nee.

  4. 4
    Lees het register .

    See prices, GST, status and the new contract sum.

  5. 5
    Laat het aftekenen .

    Verzend hangende wijzigingen aan de eigenaar voor schriftelijke goedkeuring.

Over deze tool

Variations are changes to the work in a building contract: an upgraded benchtop, extra power points, rock found during excavation, or an item the owner deletes. They are one of the main causes of disputes between builders and owners. Home building laws in every state require variations to be in writing, with a description and price, and agreed by the owner before the work is done, with limited exceptions. Builders usually add a margin to the cost of a variation to cover overheads and profit, often 15 to 25%, and then GST at 10%. This calculator prices each variation with your margin and GST, keeps a register showing which are approved and which are still pending, works out the adjusted contract sum, and shows how much the variations have changed the original price.

Who this is for

Builders, renovators and trade contractors who price variations, and home owners who want to check variation claims.

How a variation is priced

Variation price = cost of labour and materials × (1 + margin) + GST at 10%. For a credit, such as a deleted item, the cost is entered as a negative number and no margin is added, though contracts can say otherwise. Your contract may set the margin for variations; use that figure.

Entering variations

Write one variation per line: number, description, cost excluding GST and margin, and whether the owner has approved it (yes or no). For example, `V1, Upgrade benchtop to stone, 4200, yes`.

The register

The table shows each variation's cost, the price after margin, the GST and the total, with its status. The summary gives: - the original contract sum including GST, - approved variations, - the new contract sum, - pending variations still to be agreed, - the percentage change from the original price, - the margin earned on approved variations.

Getting variations right

- Put every variation in writing before the work, with a description, price and any change to the completion date. - Get the owner's signature or written approval. - Number variations and keep a running register. - Include variations in progress claims only once approved. Some states set rules for variations required by an authority or emergency, and some limit when a builder can claim for work done without a signed variation.

For owners

Ask for the cost breakdown and the margin used. Compare the price with what you would pay for the item separately. Check whether a variation also extends the completion date.

Worked example

On a A$385,000 contract including GST, with a 20% margin: an upgraded stone benchtop at A$4,200 cost, six extra power points at A$780 and a garden shed deleted for a A$2,400 credit add A$3,934 to the contract, a 1.0% increase. Rock excavation at A$6,500 cost (A$8,580 with margin and GST) is pending.

Limits

An estimate, not legal advice. Your contract terms and your state's home building laws decide how variations must be made and paid.

Uitgewerkt voorbeeld

Drie goedgekeurde variaties voegen A$3.934 toe aan een contract van A$385.000; er hangt nog één ter waarde van A$8.580 af.

In het kort

Veelgestelde vragen

Hoe maken bouwers prijsvariaties?

Kosten plus een marge, vaak 15 tot 25%, plus GST.

Moet een wijziging schriftelijk worden ingediend?

Ja, de huisbouwwetten in elke staat vereisen in de meeste gevallen schriftelijke variaties.

Wordt de GST aan variaties toegevoegd?

Ja, 10% voor een geregistreerde bouwer.

Hoe worden verwijderde items behandeld?

Als krediet; voeg een negatieve kost in.

Kan een bouwer kosten in rekening brengen voor niet-ondertekende variaties?

Vaak niet, of alleen in beperkte gevallen; controleer de wet van uw staat.

Zijn mijn gegevens opgeslagen?

Alleen in je browser.

Helemaal gratisGeen kosten, geen registratie
Bestanden blijven privéAlles draait in je browser
Makkelijk in je eigen taalBeschikbaar in veel talen