Project Budget and Earned Value Tracker
Enter task budgets, dates, progress and actual costs to get earned value indices, forecasts at completion and an S-curve for the project.
Работи във вашия браузър. Файловете ви никога не напускат устройството. Вижте как да го проверите
…
Как се прави
- 1Name the project
Enter the project name, currency and status date.
- 2Add tasks
In Tasks and progress add each task with category, start, end and budget.
- 3Report progress
Set percent complete for the status date with the slider or number.
- 4Log costs
Add cost lines in Actual costs or import a CSV of invoices.
- 5Read the dashboard
Check PV, EV, AC, CPI, SPI, EAC, TCPI, earned schedule and the S-curve.
- 6Compare tasks
Open Planned vs actual to find the tasks and categories driving variance.
- 7Report
Print the status report PDF or export Excel and CSV.
За този инструмент
A budget spreadsheet tells you how much you have spent, but not whether that spending bought the progress it should have. Earned value management answers that by comparing three numbers at a status date: the planned value of work scheduled so far, the earned value of work actually done, and the actual cost. From them come the cost and schedule performance indices and a forecast of what the project will cost at completion. This tracker does the arithmetic for you. Enter each task with a budget, start and end dates and percent complete, log actual costs as invoices arrive, and the dashboard shows every standard indicator with traffic-light colours, an S-curve of PV, EV and AC, a per-task planned-versus-actual table and a printable status report.
Who this is for
Project managers reporting to sponsors, construction and engineering teams, IT and consultancy projects, grant-funded programmes and students learning earned value for PMP or PRINCE2 exams.
Tasks and progress
Each task has a name, a category (labour, materials, other), a budget, a start and end date and a percent complete. Percent complete is saved for the status date, so moving the status date back shows earlier progress and the S-curve keeps its history. Planned value spreads each budget evenly over the task's calendar days.
Actual costs
Log every cost with a date, task, amount and note, or import a CSV with Date and Amount columns (a Task column is matched by name). Costs dated after the status date are greyed out and not counted.
The indicators
- PV, planned value: budget of the work scheduled by the status date. - EV, earned value: budget × percent complete for each task. - AC, actual cost: money spent up to the status date. - CV = EV − AC and SV = EV − PV: negative means over budget or behind schedule. - CPI = EV ÷ AC and SPI = EV ÷ PV: below 1.00 is worse than plan. - EAC = BAC ÷ CPI: the usual forecast if the cost trend continues. The tool also shows AC + (BAC − EV) for a one-off overrun and AC + (BAC − EV) ÷ (CPI × SPI) when the schedule also drives cost. - ETC = EAC − AC, VAC = BAC − EAC and TCPI = (BAC − EV) ÷ (BAC − AC), the efficiency needed from now on to finish on budget.
Earned schedule
SPI drifts back to 1.00 at the end of every late project, because all work is eventually earned. Earned schedule fixes this by measuring time: ES is the date at which planned value equalled today's earned value, and SPI(t) = ES ÷ actual time. The forecast finish date divides the planned duration by SPI(t).
Charts and reports
The S-curve plots PV over the whole plan and EV and AC up to the status date, with a dashed forecast towards EAC. Planned vs actual shows each task's budget against actual cost and a summary by category. Status report PDF prints the indicators and the task table; Excel exports tasks, costs and the S-curve data.
Worked example
A project has BAC 100,000. At the status date PV is 50,000, EV 40,000 and AC 45,000. CV is −5,000, SV −10,000, CPI 0.889 and SPI 0.80. EAC = 100,000 ÷ 0.889 = 112,500, ETC 67,500 and VAC −12,500. To still finish on budget the remaining work would need TCPI 60,000 ÷ 55,000 = 1.09.
Limits
Earned value is only as honest as the percent-complete figures; agree a rule such as 0/50/100 per cent for small tasks. Planned value assumes even spending across calendar days, not resource-loaded schedules or working calendars. Forecasts are trends, not promises, and this is not accounting or contractual advice.
Решен пример
BAC 100,000; PV 50,000, EV 40,000, AC 45,000 → CPI 0.89, SPI 0.80, EAC 112,500, TCPI 1.09.
Накратко
- Категория: Бизнес и работа
- Работи в браузъра, без регистрация, без качване.
- Въведената от вас информация остава на устройството ви.
- Налично на английски.
- Съдържанието е прегледано последно:
- Официален източник: PMI Practice Standard for Earned Value Management and the US GAO Cost Estimating and Assessment Guide (EV, PV, AC, CPI, SPI, EAC, TCPI); earned schedule after Lipke
Често задавани въпроси
What is a good CPI?
1.00 means you get one unit of value per unit spent. Below 0.90 usually needs action; above 1.00 is under budget.
Which EAC should I report?
BAC ÷ CPI is the standard trend forecast. Use AC + (BAC − EV) only if the overrun was a one-off that will not repeat.
Why does my SPI look fine at the end of a late project?
Classic SPI always returns to 1.00 when work is finished. Use SPI(t) from earned schedule instead.
How do I measure percent complete?
Use objective rules where you can: milestones reached, units installed or 0/50/100 per cent for short tasks.
Can I track several status dates?
Yes. Progress is stored per status date and costs carry dates, so earlier dates recalculate correctly.
Is the data private?
Yes. It stays in this browser unless you export a file.
